Dripping Springs ISD New WSES & DSMS Reno

New elementary school to be added to Dripping Springs Middle School Site

Approximately 105,000 sf Addition & 60,000 Renovation

  • Building Drawings – Late January 2020
  • Building Bid – Late February 2020

Anticipated start date April 2020, Work to be completed June 2021

 

Offsite Force Main and pump station

Approximately 2,700 lf force main with pump station

  • Drawings – Mid October 2019
  • Bid – Mid November 2019

Anticipated start date December 2019, Work to be completed March 2020